Development Project
ABLAINCOURT (80)



LOCATION
2 SITES:
Ablaincourt 1 => 20.7 ha land area, logistics platform delivered in 2023
Ablaincourt 2 => 4.9 ha land area in the municipality of Ablaincourt-Pressoir, at the foot of the Haute Picardie TGV Station, at the intersection of the A29 and A1 motorways, 45 km from Amiens and 120 km North of Paris
| Land | Leasable Area | Parking | Number of Units | Area per Unit |
|---|---|---|---|---|
| Area 49,672 m² |
Warehouse: 21,700 m² Offices: (3.5%) 813 m² Technical rooms: 283 m² Total: 22,796 m² |
65 light vehicle spaces 4 heavy vehicle spaces |
4 | 5,300 m² |
| Truck Yard | Dock Doors | Ground-Level Sectional Doors | Slab | Clear Height |
|---|---|---|---|---|
| 35 m | 24 | 2 | 5 t/m² | 11.8 m |
| Building Permit | ICPE Classification |
|---|---|
|
Obtained and cleared ICPE Obtained and cleared |
Categories: Registration: 1510 Declaration: 2925 / 2910 |
ABLAINCOURT 1
Logistics Platform
| Land Area: | 207,838 m² | Logistics | 35,894 m² |
| Available Area: | 37,866 m² | Offices | 1,340 m² |
| Charging Room | 632 m² |

Technical Description
- ✅ Building with 16 cells of approximately 5,985 m² delivered in 2023, including 6 cells available for lease
- ✅ ICPE 1510 – Low-threshold Seveso
- ✅ Clearance height of 11.80 m
- ✅ Warehouse certified BREEAM Very Good
- ✅ 2 ground-level accesses
- ✅ Truck yard of 35 m
- ✅ 38 heavy vehicle loading docks equipped with manual insulated sectional doors & hydraulic levelers
- ✅ Light and heavy vehicle parking spaces

ABLAINCOURT 2
Logistics Platform
Land Area: 49,672 m²
Built Area (SDP + LT): 22,796 m²
Total Area (SDP): 22,513 m²
Logistics: 21,700 m²
Offices: 813 m²

TECHNICAL DESCRIPTION
- ✓ Building with 4 cells of approximately 5,300 m²
- ✓ Clearance height of 11.80 m
- ✓ BREEAM certified warehouse
- ✓ Full LED lighting
- ✓ 24 loading docks equipped with manual insulated sectional doors & hydraulic levelers
- ✓ 2 ground-level accesses
- ✓ 35 m truck yard
- ✓ Light vehicle parking: 65 spaces
- ✓ Heavy vehicle parking: 4 spaces (with turning area)
- ✓ PV-ready roof
Administrative authorizations obtained & cleared:
Building Permit ⇒ 2023-07-03
ICPE ⇒ 2023-06-20
Registration under section: 1510
Declaration under sections: 2925 & 2910